Important Notes

  1. Before the acceptance tests, ensure that the TrustZone feature has been preset on the server. That is, the iTrustee secure OS and matched iBMC and BIOS firmware have been installed on the server.
  2. Ensure that both parties agree on the test items for the acceptance.
  3. During the product acceptance and preliminary acceptance tests, both parties should strictly observe applicable test criteria.
  • In the acceptance tests, observe the contracts and agreements between the two parties concerned. This document serves as a reference only.
  • Check whether TrustZone-related firmware has been installed on the server; for details, see BIOS settings described in Setting Up the TA and CA Operating Environment. If the TEE function can be enabled, the firmware has been installed.